Indicative investment, across the whole spectrum.

Indicative figures, August 2026, hardware excluding VAT. IT cost per MW varies by more than 3× with density: ~€15–40M/MW for CPU clusters, €75–95M/MW for liquid-cooled accelerated HPC/AI systems; NVMe storage and high-memory nodes exceed €150M/MW.

Investment | Budget finder

What does your budget build?

Move the slider to a budget. Every configuration whose published range includes it lights up, together with the work it is built for.

€500€500M

2 configurations fit this budget

  • Storage server or array

    €38–331k

    Dedicated capacity for data — the range runs from a disk-based server to an all-flash array.

    Typical workloads

    • Network file shares (NAS)
    • Backup and archiving
    • Large research datasets
    • Shared storage for virtual machines
  • CPU rack (private cloud)

    €250–900k

    A full rack of servers, storage and networking, run as one platform.

    Typical workloads

    • Private cloud and virtualisation
    • Consolidated company IT
    • A small HPC cluster
    • Disaster-recovery site

Indicative figures, August 2026, hardware excluding VAT. IT cost per MW varies by more than 3× with density: ~€15–40M/MW for CPU clusters, €75–95M/MW for liquid-cooled accelerated HPC/AI systems; NVMe storage and high-memory nodes exceed €150M/MW. Tier 07 is calibrated on European public procurement 2024–2026, where the mid-segment — the one reachable by a specialist integrator — sits at €12–40M, not at exascale. High volatility on GPUs and memory — firm quotes are valid for 30 days. Final pricing on request.

Investment | Construction

Data-centre construction in Romania — 2026 benchmarks.

0.1–0.3 MW | IT capacity

Server / HPC room

Cost per MW

€18–35M

Total project

€1.8–8.7M

Below 1 MW the €/MW metric loses its meaning: plant rooms, UPS, batteries, generator and suppression do not shrink with power, so a 0.3 MW facility ends up at ~2.7× the per-MW cost of a hyperscale build.

Cost per MW, all seven compared

Complete facility (structure + MEP), excluding VAT; includes the grid connection, excludes land and IT equipment. Cost per m² is measured against gross built area, not white space — the international $600–1,100/sq ft benchmark is also on gross area, and applying it to the technical floor underestimates the budget several times over. In a small-scale HPC centre the gross-to-white-space ratio reaches 9:1, because plant rooms, UPS, batteries, generator and suppression do not shrink. Below 1 MW, the €/MW metric loses its meaning: the same fixed costs do not fall in proportion to power, and a 0.3 MW facility ends up at ~2.7× the per-MW cost of a hyperscale build. Calibrated on a real project: a 300 kW IT hall built to Tier III standard with liquid cooling, in a ~1,800 m² building, lands at €5.5–8.7M for the facility. Figures are on a July 2026 basis; Romanian construction costs are rising ~10% a year, so facility quotes are issued with 60-day validity and an INS indexation clause. A 20–30% premium applies in Bucharest / Cluj versus secondary cities.

Investment | Worked examples

Five real configurations, with the full budget.

Five real configurations, with the full budget
ExampleConfigurationHardware / ITFacility
AI workstation2× 96 GB GPU, 512 GB RAM, NVMe€30–36k—
Training server8× GPU (141–288 GB), 8× 400G, DLC€440–520k—
Small server room50 kW IT, 40 m², 12 racks, N+1€0.5–1.2M€0.4–0.8M
Departmental HPC hall300 kW IT, 190 m² technical, ~3–8 PF FP64€6–10M€5.5–8.7M
10 PF FP64 supercomputer≈0.3 MW IT, extensible 1,800 m² building, Tier III€12–28M€5.5–8.7M

Total investment

Workstation €32–41k | training server €465–555k | server room €0.95–2.1M | HPC hall €12.5–20M | 10 PF supercomputer €18–40M — including the Kronsavier fee.

Public EuroHPC comparators

Mid-segment, 2026: CASPIr (IE, 15 PF) — €25M | Mimer AIF (SE) — €29.8M | DAEDALUS (GR, 89 PF) — €36M. Large scale: LUMI (FI, 380 PF) — €144.5M | JUPITER (DE, exascale) — €273M. Contract values, including delivery, installation and maintenance.

Indicative figures, August 2026, excluding VAT; land and grid connection excluded. Cost per PF varies sharply with architecture: FP64-optimised systems are significantly more efficient per euro than AI-training-optimised ones.

Let's build